Mountain Valley Pipeline Proposal

Mountain Valley Pipeline Southgate Extension: proposed pipeline to transport fracked gas through Alamance and Rockingham counties 

The Mountain Valley Pipeline (MVP) is a 303 mile pipeline being constructed to carry fracked gas from West Virginia into Virginia.  MVP is working to get approval for an extension of that pipeline that will take it an additional 70 miles from southern Virginia into central North Carolina. The addition, the MVP Southgate project, will cut through Rockingham and Alamance counties, ending at a point just south and east of Graham, below 1-85-40.


Recent Updates!

MVP Southgate’s 401 permit has been denied!

The Mountain Valley Pipeline (MVP) is a 303 mile pipeline being constructed to carry fracked gas from West Virginia into Virginia. MVP is working to get approval for an extension of that pipeline, MVP Southgate, that will take it an additional 70 miles from southern Virginia into central North Carolina. If approved, the MVP Southgate project will cut through Rockingham and Alamance counties, ending at a point just south and east of Graham, below 1-85-40.

Haw River Assembly first learned about MVP Southgate in April of 2018. At this point, we held community meetings and sent mailings to every home along the proposed route. Neighbors started talking to each other and refusing access to surveys for the project. As a coalition of landowners, impacted community members, and environmentalists, we presented and gave public comment at every town and county commissioners meeting along the proposed route. Through this work, every town and county was made aware of their rights and heard the voices of their communities saying “we don’t want or need this project.” Alamance county unanimously signed a resolution to oppose the project, as did several towns along the route.

In early August of 2020, NC Department of Environmental Quality denied the 401 permit, which is the permit necessary to cross streams.
The permit was denied outright, meaning there were no conditions under which MVP Southgate could make corrections and resubmit. NCDEQ’s denial letter focused predominantly on the failures of the MVP mainline.
“Division staff have determined the Southgate project’s sole utility and purpose is tied to and wholly relies on the completion of the entire Mainline project,” DEQ’s letter reads. “The uncertainty of the MVP Mainline Project’s completion presents a critical risk to the achievability of the fundamental purpose of MVP Southgate,” it continued.
Most of the environmental harm would occur during construction, the division wrote, adding that it “finds it is inappropriate to unnecessarily risk impacting high-quality waters and drinking water supplies of North Carolinians.”

MVP Southgate has appealed the denial decision.Theoretically, if MVP mainline gets their permits and legal challenges resolved, MVP Southgate could reapply. The mainline is currently under a stop work order and faces several legal challenges. Additionally, this denial of the Southgate permit makes the mainline permit less profitable with an uncertainty of delivery and increased capacity.
This uncertainty around the worthiness of investing vast sums of money in a project that suffers from progressively decreasing certainty of success (and profit returns) is what killed the ACP. It can kill the MVP too.

MVP Mainline

On October 9, Mountain Valley Pipeline (MVP) was given another two years to complete a natural gas pipeline already marked by six years of community opposition, environmental damage, legal fights and delays. The Federal Energy Regulatory Commission also lifted a stop- work order for all but a 25-mile segment of the interstate transmission line that includes the Jefferson National Forest and adjacent land. (Roanoke Times)
On October 16, the Fourth Circuit Court of Appeals imposed a temporary stay on MVP’s Nationwide 12 permits that had been requested by the Sierra Club, Appalachian Voices and other environmental groups battling the 303-mile mainline project through West Virginia and Virginia.
“It’s a setback for the pipeline, which had been given the go-ahead last week to resume construction after a months long delay by the Federal Energy Regulatory Commission as well as receiving the key permits it needed. One of those permits, the so-called Nationwide 12 permit from the Army Corps of Engineers, is at issue in this temporary stay while a full stay is considered.” (Pittsburgh Business News)
A Draft Supplemental Environmental Impact Statement (SEIS) regarding MVP’s permit to cross national forests was recently posted in the Federal Register, initiating a 45 day comment period, ending November 9. The SEIS is used to determine whether or not a project, in this case the Mountain Valley Pipeline, can be permitted to cross a national forest. To comment or sign on to comment petitions visit POWHR’s How-To Comment Guide.
The Mountain Valley Watch needs volunteers to monitor construction and review aerial images. Sign up through the MVWatch Volunteer Interest Form. A virtual training is planned for November 1 and information will be sent to the volunteer list and posted on the MVWatch Facebook page.

Tell the State to Deny MVP’s 401 Permit
The MVP Southgate extension through Pittsylvania county, VA to Rockingham and Alamance counties in North Carolina would be an orphaned pipeline if MVP were to meet the same fate as the recently cancelled Atlantic Coast Pipleine (ACP) which seems more likely as the legal battles continue. NC DEQ has until August 9th to approve or deny the stream crossing permit for MVP Southgate. This pipeline is unnecessary and would cause irreparable damage to our waterways, environment, and communites and tie us to a dying fossil fuel economy for decades.The Southgate extension should be denied outright. We do not need additional fracked gas infrastructure in our state!
 
Use our online action form to send a message to the state opposing MVP by August 8.
 
 
 
Pipelines:  ACP Cancelled,  MVP Southgate Next?
In a surprise move on July 4th,  Dominion and Duke Energy announced that they were cancelling their $8 billion fracked gas Atlantic Coast Pipeline after years of challenges, permit delays and ballooning costs.  We’re cheering for all of our environmental partners and communities in NC and VA that have been fighting for this win for over six years. Now we’re going to be doubling down to make sure MVP and MVP Southgate meet the same fate.
There have been multiple publications citing the lack of need for additional pipeline infrastructure and fossil fuel sources in North Carolina and across the southeast. North Carolina is one of the leading states in solar power, and Gov. Cooper’s Executive  Order 80 commits us to lowering Greenhouse Gas emissions to 40% below 2005 levels. New pipeline projects do not fall within that commitment.
The MVP mainline has been met with several legal battles and water quality violations, and is still under a stop work order. In May, two MVP customers amended a 2016 agreement to terminate the deal if service doesn’t begin by the end of 2021. That goal is looking more and more unlikely. NCDEQ is in the process of reviewing information submitted for MVP Southgate’s 401 stream crossing permit. They requested more information in mid June, and received a response that did not address all of the concerns laid out by NCDEQ. NCDEQ also requested an update on MVP mainline actions, including a detailed list of all water quality violations, status of permits, and all legal challenges to date. They are keeping a close eye on the status of the MVP mainline project, and we hope they will deny the 401 permit for the Southgate project in the coming weeks.
 
 

Federal judge upholds ban on process for permitting pipelines, including Mountain Valley
Environmentalists have argued for years that the Army Corps’ process, called a Nationwide Permit 12, takes a “blanket approach” that does not adequately assess a pipeline’s crossing of each stream or wetland in its path.

“Constructing pipelines through rivers, streams and wetlands without analyzing the impacts on imperiled species is unconscionable, and we will continue to fight to protect vulnerable species, our waters and the climate from such reckless development,” Jared Margolis, a senior attorney with the Center for Biological Diversity, said in a statement.


How this Pipeline Poses Threats to our Environment and Communities

The extractive process of fracking is destructive to land, air, and water quality in many ways, but the transport of the fracked gas also poses threats to downstream communities. In the construction process of pipelines, easements must be cleared of all trees and plants, exposing the disturbed land to erosion and causing sedimentation in streams. In-stream sedimentation not only carries nutrients and chemicals into the water, but the sediments themselves drown sensitive wildlife habitats in nearby streams. The MVP Southgate proposed route must cross several streams and tributaries. In order to do this, ditch lines are often blasted through rock and streams to lay the pipe. Streams are then dammed up and rerouted during trench construction, or drills cut a route under the stream using hydraulic motors and jet nozzles. Both of these processes destroy stream habitat. Potential leaks in pipes pose ongoing threats to water quality for downstream users. Fracked  gas is also highly explosive. Recent explosions have caused serious injuries and destroyed homes. By allowing this pipeline into our communities, we are tying ourselves to decades of fossil fuel use, resulting in high methane emissions and heightening our effect on climate change.


Effects on the Haw

MVP maps show that it will run adjacent to the Haw through Rockingham and Alamance counties. The pipeline will cross many streams in the Haw River watershed, and alternative maps have shown crossing the Haw River twice. Not only is the destruction of the land and forest a threat to our watershed, but the processes used in stream crossings leave streams devastated. The pipes themselves have a high potential of leaking and natural gas pipeline explosions are not uncommon in the United States. There have been 4 since June, including 1 fatality.  MVP has a legacy of abusing community members and landowners by providing minimal compensation for land, or using eminent domain to take the land if landowners refuse.

Duke’s Integrated Resource Plan includes details for 50/50 conversions of unused coal plants to natural gas plants. If this proposed addition is allowed, we can expect more pipelines to connect to converted natural gas plants. This could mean a new pipeline through Guilford County to the  Belews Creek station.

More information, organizing materials, resources and updates can be found at this website:  No Mountain Valley Pipeline”  


Are you a landowner who has been contacted by Mountain Valley Pipeline or Doyle Land Surveying?

Know your rights. You have the right to say NO. Your ability to refuse to negotiate and require the energy companies to use eminent domain is one of the most powerful statements you can make to protect your land. It gives you the most influence afforded to you by the Federal Energy Regulatory Commission (FERC). The pipeline company does NOT have the right of eminent domain until they have been issued a Certificate of Public Convenience and Necessity from FERC. Surveyors do not have the right to be on your private property without your permission.

Click here for more information about what your rights are as a property owner.

General Information

  • Pipeline extension from Mountain Valley Pipeline mainline in Pittsylvania County, VA.
  • 70 miles of pipeline through Rockingham and Alamance County mostly in the Haw River watershed
  • Size of pipeline is could be up to 24” in diameter.
  • Pipeline will require  100’ of easement during construction,and a 50′ permanent easement.
  • Route will run adjacent to the Haw in many areas, cutting across sensitive streams and tributaries.
  • Destination is east of Graham and south of I-40-85
  • “Fracked” shale gas running through pipelines is sourced from the Utica and Marcellus shale fracking operations in WVA and PA, and is owned by PSNC.
  • Pre-filing permit processes will begin in May 2018. MVP will then hold community open houses though the route corridor to “identify and resolve environmental issues.”
  • MVP aims to begin construction by 2020.

Wins
This is a long fight, so let’s not forget the progress we’ve made!

  • Alamance County commissioners signed a unanimous resolution to oppose the pipeline project
  • Elon University student government signed a resolution to oppose the pipeline project
  • Stoneville signed a resolution to oppose the project
  • NC DEQ wrote a critical letter of the project, stating they saw no demonstrated need
  • Every local government body along the proposed route in Alamance County has heard a presentation or public comments from us in opposition of the pipeline project.
  • NCDEQ rejected MVP Southgate’s first attempt to apply for the 401 certificate.
  • City of Burlington writes critical comments to oppose the project
  • 39 state legislators sign a letter to oppose the project
  • Over 30 people turn out to speak in November 2019 against MVP’s second attempt to get a 401 certification for stream crossing impacts. (We expect to hear in February what NCDEQ decides)

Donate to Help Us Organize Against the Mountain Valley Pipeline:

These donations will be earmarked to create materials and mailings to organize in order to stop the pipeline.

MVP Southgate Updates

Sign up for the listserv to stay up to date here

See the most recent blog posts here

See the MVP Southgate Facebook Page

Whats happening with MVP Mainline?